Friday, August 17, 2018


Work Performed:


·        Excavation and under cuts in phase 2
  •  Tuesday the water connection at Landwehr and Crestwood will be completed.
  • Started installing the string line for curb instalation

 

Work Anticipated to be performed, August 20th to August 24th
 



 
  • Friday set string line for the curbs and Friday start the curb pour for phase two.
  • Monday weather permitting the contractor will start to pour new curbs in phase 2



The roadway reconstruction phase is still in full swing and working on the second of three phases for the concrete curb & gutter / asphalt paving operations. Monday weather permitting the contractor will start to pour new curbs in phase 2. This phase, resident in Phase 2 will be without driveway access until Thursday, August 30th, if all goes as planned and weather allows for construction operations. We understand this is a huge inconvenience to each of the residents without driveways access; therefore, we are doing everything possible to minimize it to the greatest extent possible. Driveway access is for an extended period of time to allow for all the work to be completed at one time in lieu of staggered driveways restrictions several times over the next few weeks. Once access is restored, a majority of the roadway work in front of your home will be completed, including the first layers of asphalt binder which will significantly reduce the amount of dust and provide for a smooth driving surface. 

 
Once the work in Phase II is completed, the next phase of roadway reconstruction will begin. That section will be from 3921 Crestwood to Pfingsten Road.

Thank you in advance to all those  residents without driveway access for the next twelve days, your patience and understanding is greatly appreciated.

Friday, August 3, 2018

Excavation and Curbs opngoing in Phase II


Work Performed:


·        Grading of new aggregate base in Phase I
  • Bituminous Binder course complete in phase one
 

 

Work Anticipated to be performed, August 13th to August 17th

·        The intersection of Sussex and Crestwood will be excavated and aggregate base installed on Monday August 13th.. Notices have been passed out in anticipation of this work
  • Tuesday the water connection at Landwehr and Crestwood will be completed.
  • Roadway excavation and aggregate base course installation from Sussex Lane to 3924 Crestwood. 
  • Thursday set string line for the curbs and Friday start the curb pour for phase two
     

    The roadway reconstruction phase is still in full swing and working on the first of three phases for the concrete curb & gutter / asphalt paving operations. During this phase, resident with new concrete curb & gutter will be without driveways access until Tuesday, August 21st, if all goes as planned and weather allows for construction operations. We understand this is a huge inconvenience to each of the residents without driveways access; therefore, we are doing everything possible to minimize it to the greatest extent possible. Driveway access is for an extended period of time to allow for all the work to be completed at one time in lieu of staggered driveways restrictions several times over the next few weeks. Once access is restored, a majority of the roadway work in front of your home will be completed, including the first layers of asphalt binder which will significantly reduce the amount of dust and provide for a smooth driving surface. 

 
Once the work in Phase II is completed, the next phase of roadway reconstruction will begin. That section will be from 3921 Crestwood to Pfingsten Road.

Thank you to all those  residents without driveway access over the past week, your patience and understanding is greatly appreciated.

Friday, July 27, 2018

Phase I Curb and Gutter and Paving On-Going.

Work Performed:
·         Roadway excavation and new base course installation within cul-de-sacs
·         Roadway excavation and new base course installation along Crestwood Drive from Sussex Lane to Landwehr Road
·         Concrete curb & gutter installation within west and center cul-de-sacs
·         Concrete curb & gutter installation along Crestwood Drive from Carousel Drive (West) to Landwehr Road

Work Anticipated to be performed, July 30th to August 3rd  
·         Roadway excavation and installation of new base course along Crestwood Drive from Sussex Lane to Pfingsten Road
·         Work along Crestwood Drive from Carousel Drive (West) to Landwehr Road
o   Complete concrete curb & gutter installation
o   Replace concrete driveways
o   Replace concrete sidewalks, as planned
o   Fine grade roadway in preparation for asphalt paving
o   Adjust structures within curb & gutter
o   Pave 1st Layers of asphalt pavement (scheduled for early the week of August 6th)

The roadway reconstruction phase is in full swing and working on the first of three phases for the concrete curb & gutter / asphalt paving operations. During this phase, resident with new concrete curb & gutter will be without driveways access until Tuesday, August 7th if all goes as planned and weather allows for construction operations. We understand this is a huge inconvenience to each of the residents without driveways access; therefore, we are doing everything possible to minimize it to the greatest extent possible. Driveway access is for an extended period of time to allow for all the work to be completed at one time in lieu of staggered driveways restrictions several times over the next few weeks. Once access is restored, a majority of the roadway work in front of your home will be completed, including the first layers of asphalt binder which will significantly reduce the amount of dust and provide for a smooth driving surface. 

Once the work in Phase I is completed, the next phase of concrete curb & gutter / asphalt paving will begin. That section will be from Carousel Drive (West) to 3924 / 3921 Crestwood Drive. Again these residents will be out of their driveways for approximately 1.5 weeks. Residents will be notified of the exact dates for driveway restrictions as the schedule is finalized.

Thank you to all those residents without driveway access over the next week, your patience and understanding is greatly appreciated.

Saturday, July 21, 2018

Roadway Excavation On-Going

Work Performed:
·         Completed storm sewer replacements
·         Completed sanitary sewer service replacements
·         Started roadway excavation and installation of new aggregate base materials within the cul-de-sacs

Work Anticipated to be performed, July 23rd to July 27th   
·         Complete roadway excavation and installation of new aggregate base materials within cul-de-sac
·         Begin roadway excavation and installation of new aggregate base materials along Crestwood Drive
·         Pour concrete  curb & gutter within cul-de-sacs.

As roadway excavation along Crestwood Drive begins, the roadway will be impassible in the areas they are working during the day, with access to driveways and roadway restored at the end of each day. The time it will take to perform this work will largely depend on the amount of excavation needed to get to a stable base material.  Due to not knowing how long it will take to perform the roadway excavation due to unknown soils under the roadway, we are unable to provide exact dates work will be on-going in front of your home; however, we will attempt to notify you the day prior so you can remove any vehicles from driveways and garages. When traveling along Crestwood Drive, please be patient and travel carefully as a lot of equipment and semis are accessing the site to remove excess spoils and deliver new aggregate materials. We also ask that you access your homes via the neighborhood and side streets when possible.  We understand this is a significant inconvenience, but are committed to doing everything possible to limit delays to the greatest extent possible.

Thank you in advance for your patience.

Sunday, July 15, 2018

Roadway Reconstruction to Begin

Work Performed:
·         Minimal work completed due to scheduling conflicts and waiting on needed permits to work along Landwehr Road.
·         Resumed performing sanitary sewer service replacements as planned
·         Resumed storm sewer installation within cul-de-sacs
·         Started making storm sewer repairs as previously determined.

Work Anticipated to be performed, July 16th to July 20th  
·         Complete storm sewer replacement
·         Begin roadway excavation.

The contractor will be transitioning to the roadway reconstruction phase of the project.  This work will include removing the remaining concrete pavement, excavating the existing base materials until a stable base is established, installing new base materials, concrete curb & gutter on both sides of the street, and new asphalt pavement.  The roadway excavation will be broken up into sections to minimize the inconvenience to residents to the greatest extent possible. However, the roadway will be impassible in the areas they are working during the day, with access to driveways and roadway restored at the end of each day. The time it will take to perform this work will largely depend on the amount of excavation needed to get to a stable base material. Additional information will be provided to residents during the roadway reconstruction phase.

Thank you for your understanding and patience during some of the unexpected delays.

Friday, June 29, 2018

Underground Work Mostly Completed. No Work On-site week of July 2nd due to Holiday

Work Performed Last Week, June 25th to June 29th
·         Completed water service replacements for entire project
·         Connected new water main to existing water main along side streets
·         Abandoned existing water main along Crestwood Drive
·         Performed sanitary sewer service replacements as needed.
·         General site clean-up

Work Anticipated to be performed next week, July 2nd to July 6th
·         No work anticipated to be performed on-site all week due to July 4th Holiday
·         General site clean-up, as needed.

The underground utility portion of the project is mostly completed at this time. The contractor will have a few sanitary sewer services to complete, minimal storm sewer installation, and one final water main abandonment to complete.

Following the July 4th Holiday, the contractor will be transitioning to the roadway reconstruction phase of the project.  This work will include removing the remaining concrete pavement, excavating the existing base materials until a stable base is established, installing new base materials, concrete curb & gutter on both sides of the street, and new asphalt pavement.  The roadway excavation will be broken up into sections to minimize the inconvenience to residents to the greatest extent possible. However, the roadway will be impassible in the areas they are working during the day, with access to driveways and roadway restored at the end of each day. The time it will take to perform this work will largely depend on the amount of excavation needed to get to a stable base material. Additional information will be provided to residents as the schedule is finalized and provide parking and driveway restrictions.

Thanks again for all your understanding as the project moves into the next phase of construction and the various inconveniences that you will experience.

 

Have a safe and enjoyable July 4th Holiday.

Monday, June 18, 2018

Water Service Replacements On-Going.

Work Performed Last Week, June 11th to June 15th  
·         Water service replacements along Crestwood.

Work Anticipated to be performed next week, June 18th to June 22nd  
·         Continue with water service replacements along Crestwood Drive
·         Water service replacements within the cul-de-sacs
·         Connection between new water main and existing water main at Carousel Drive (East) and Crestwood Drive.
·         Storm sewer improvement with cul-de-sacs as water service replacements are performed.

The contractor will continue water service replacements this week. The contractor is anticipating to complete the water services along Crestwood Drive and begin working in the cul-de-sacs. Water services will be replaced from the new water main to the existing valve and box located in front of each home. During the water service replacement, water to individual homes will be shut-off for approximately 1-2 hours while the transition from the old service to the new service is made. The contractor will notify each resident individually regarding the approximate time and day of the water shut-off prior to turning off the water.

The water service replacements within the cul-de-sacs will be time consuming due to the routing and length of each service.  It will be increasingly difficult to travel through the cul-de-sacs as this work is on-going.  Please be patient while driving through these areas.

Thanks again for all your assistance while you live through construction in your area.