Sunday, July 15, 2018

Roadway Reconstruction to Begin

Work Performed:
·         Minimal work completed due to scheduling conflicts and waiting on needed permits to work along Landwehr Road.
·         Resumed performing sanitary sewer service replacements as planned
·         Resumed storm sewer installation within cul-de-sacs
·         Started making storm sewer repairs as previously determined.

Work Anticipated to be performed, July 16th to July 20th  
·         Complete storm sewer replacement
·         Begin roadway excavation.

The contractor will be transitioning to the roadway reconstruction phase of the project.  This work will include removing the remaining concrete pavement, excavating the existing base materials until a stable base is established, installing new base materials, concrete curb & gutter on both sides of the street, and new asphalt pavement.  The roadway excavation will be broken up into sections to minimize the inconvenience to residents to the greatest extent possible. However, the roadway will be impassible in the areas they are working during the day, with access to driveways and roadway restored at the end of each day. The time it will take to perform this work will largely depend on the amount of excavation needed to get to a stable base material. Additional information will be provided to residents during the roadway reconstruction phase.

Thank you for your understanding and patience during some of the unexpected delays.