·
Roadway excavation and new base course installation
within cul-de-sacs
·
Roadway excavation and new base course
installation along Crestwood Drive from Sussex Lane to Landwehr Road
·
Concrete curb & gutter installation within
west and center cul-de-sacs
·
Concrete curb & gutter installation along
Crestwood Drive from Carousel Drive (West) to Landwehr Road
Work Anticipated to be performed, July 30th to
August 3rd
·
Roadway excavation and installation of new base
course along Crestwood Drive from Sussex Lane to Pfingsten Road
·
Work along Crestwood Drive from Carousel Drive
(West) to Landwehr Road
o Complete
concrete curb & gutter installation
o Replace
concrete driveways
o Replace
concrete sidewalks, as planned
o Fine
grade roadway in preparation for asphalt paving
o Adjust
structures within curb & gutter
o Pave
1st Layers of asphalt pavement (scheduled for early the week of
August 6th)
The roadway reconstruction phase is in full swing and
working on the first of three phases for the concrete curb & gutter /
asphalt paving operations. During this phase, resident with new concrete curb
& gutter will be without driveways access until Tuesday, August 7th
if all goes as planned and weather allows for construction operations. We
understand this is a huge inconvenience to each of the residents without
driveways access; therefore, we are doing everything possible to minimize it to
the greatest extent possible. Driveway access is for an extended period of time
to allow for all the work to be completed at one time in lieu of staggered
driveways restrictions several times over the next few weeks. Once access is
restored, a majority of the roadway work in front of your home will be
completed, including the first layers of asphalt binder which will
significantly reduce the amount of dust and provide for a smooth driving
surface.
Once the work in Phase I is completed, the next phase of
concrete curb & gutter / asphalt paving will begin. That section will be
from Carousel Drive (West) to 3924 / 3921 Crestwood Drive. Again these
residents will be out of their driveways for approximately 1.5 weeks. Residents
will be notified of the exact dates for driveway restrictions as the schedule
is finalized.
Thank you to all those residents without driveway access
over the next week, your patience and understanding is greatly appreciated.