Friday, July 27, 2018

Phase I Curb and Gutter and Paving On-Going.

Work Performed:
·         Roadway excavation and new base course installation within cul-de-sacs
·         Roadway excavation and new base course installation along Crestwood Drive from Sussex Lane to Landwehr Road
·         Concrete curb & gutter installation within west and center cul-de-sacs
·         Concrete curb & gutter installation along Crestwood Drive from Carousel Drive (West) to Landwehr Road

Work Anticipated to be performed, July 30th to August 3rd  
·         Roadway excavation and installation of new base course along Crestwood Drive from Sussex Lane to Pfingsten Road
·         Work along Crestwood Drive from Carousel Drive (West) to Landwehr Road
o   Complete concrete curb & gutter installation
o   Replace concrete driveways
o   Replace concrete sidewalks, as planned
o   Fine grade roadway in preparation for asphalt paving
o   Adjust structures within curb & gutter
o   Pave 1st Layers of asphalt pavement (scheduled for early the week of August 6th)

The roadway reconstruction phase is in full swing and working on the first of three phases for the concrete curb & gutter / asphalt paving operations. During this phase, resident with new concrete curb & gutter will be without driveways access until Tuesday, August 7th if all goes as planned and weather allows for construction operations. We understand this is a huge inconvenience to each of the residents without driveways access; therefore, we are doing everything possible to minimize it to the greatest extent possible. Driveway access is for an extended period of time to allow for all the work to be completed at one time in lieu of staggered driveways restrictions several times over the next few weeks. Once access is restored, a majority of the roadway work in front of your home will be completed, including the first layers of asphalt binder which will significantly reduce the amount of dust and provide for a smooth driving surface. 

Once the work in Phase I is completed, the next phase of concrete curb & gutter / asphalt paving will begin. That section will be from Carousel Drive (West) to 3924 / 3921 Crestwood Drive. Again these residents will be out of their driveways for approximately 1.5 weeks. Residents will be notified of the exact dates for driveway restrictions as the schedule is finalized.

Thank you to all those residents without driveway access over the next week, your patience and understanding is greatly appreciated.