Roadway Excavation On-Going

Work Performed:
·         Completed storm sewer replacements
·         Completed sanitary sewer service replacements
·         Started roadway excavation and installation of new aggregate base materials within the cul-de-sacs

Work Anticipated to be performed, July 23rd to July 27th   
·         Complete roadway excavation and installation of new aggregate base materials within cul-de-sac
·         Begin roadway excavation and installation of new aggregate base materials along Crestwood Drive
·         Pour concrete  curb & gutter within cul-de-sacs.

As roadway excavation along Crestwood Drive begins, the roadway will be impassible in the areas they are working during the day, with access to driveways and roadway restored at the end of each day. The time it will take to perform this work will largely depend on the amount of excavation needed to get to a stable base material.  Due to not knowing how long it will take to perform the roadway excavation due to unknown soils under the roadway, we are unable to provide exact dates work will be on-going in front of your home; however, we will attempt to notify you the day prior so you can remove any vehicles from driveways and garages. When traveling along Crestwood Drive, please be patient and travel carefully as a lot of equipment and semis are accessing the site to remove excess spoils and deliver new aggregate materials. We also ask that you access your homes via the neighborhood and side streets when possible.  We understand this is a significant inconvenience, but are committed to doing everything possible to limit delays to the greatest extent possible.

Thank you in advance for your patience.