Completed storm sewer replacements
·
Completed sanitary sewer service replacements
·
Started roadway excavation and installation of
new aggregate base materials within the cul-de-sacs
Work Anticipated to be performed, July 23rd to
July 27th
·
Complete roadway excavation and installation of
new aggregate base materials within cul-de-sac
·
Begin roadway excavation and installation of new
aggregate base materials along Crestwood Drive
·
Pour concrete curb & gutter within
cul-de-sacs.
As roadway excavation along Crestwood Drive begins, the
roadway will be impassible in the areas they are working during the day, with
access to driveways and roadway restored at the end of each day. The time it
will take to perform this work will largely depend on the amount of excavation
needed to get to a stable base material. Due to not knowing how long it
will take to perform the roadway excavation due to unknown soils under the
roadway, we are unable to provide exact dates work will be on-going in front of
your home; however, we will attempt to notify you the day prior so you can
remove any vehicles from driveways and garages. When traveling along Crestwood
Drive, please be patient and travel carefully as a lot of equipment and semis
are accessing the site to remove excess spoils and deliver new aggregate
materials. We also ask that you access your homes via the neighborhood and side
streets when possible. We understand this is a significant inconvenience,
but are committed to doing everything possible to limit delays to the greatest
extent possible.
Thank you in advance for your patience.