Friday, September 21, 2018

Work Performed:

 
  • Curbs and drives completed this week.
  • Binder asphalt will be completed on Saturday
 

Work Anticipated to be performed, September 24th to September 28th.
 
 
  •    Landscaping to begin next week


 
  Thank you in advance to all those  residents without driveway access for the next twelve days, your patience and understanding is greatly appreciated.

Saturday, September 15, 2018

Work Performed:

 
  • Excavation completed this week
  • Curbs and drives completed this week.
 

Work Anticipated to be performed, September 17th to September 21st
 
 
   
The roadway reconstruction phase is still in full swing and working on the third and final phase of the project. Tentatively  next week we will be fine grading the road for the placement of the asphalt binder course. Landscaping throughout the project will be occurring at the same time. We understand this is a huge inconvenience to each of the residents without driveways access; therefore, we are doing everything possible to minimize it to the greatest extent possible.  Once access is restored, a majority of the roadway work in front of your home will be completed, including the first layers of asphalt binder which will significantly reduce the amount of dust and provide for a smooth driving surface. 

 
  Thank you in advance to all those  residents without driveway access for the next twelve days, your patience and understanding is greatly appreciated.

Sunday, September 9, 2018

Work Performed:

 
  • Excavation started this week
  • Bituminous Binder in Phase 2 complete
 

Work Anticipated to be performed, September 10th to September 14th
 
 
   
The roadway reconstruction phase is still in full swing and working on the third and final phase of the project. Tentatively  next week we will continue the excavation and undercutting. Tentatively the contractor will start preparing for the curb installation. We understand this is a huge inconvenience to each of the residents without driveways access; therefore, we are doing everything possible to minimize it to the greatest extent possible. Driveway access is for an extended period of time to allow for all the work to be completed at one time in lieu of staggered driveways restrictions several times over the next few weeks. Once access is restored, a majority of the roadway work in front of your home will be completed, including the first layers of asphalt binder which will significantly reduce the amount of dust and provide for a smooth driving surface. 

 
  Thank you in advance to all those  residents without driveway access for the next twelve days, your patience and understanding is greatly appreciated.