Friday, August 3, 2018

Excavation and Curbs opngoing in Phase II


Work Performed:


·        Grading of new aggregate base in Phase I
  • Bituminous Binder course complete in phase one
 

 

Work Anticipated to be performed, August 13th to August 17th

·        The intersection of Sussex and Crestwood will be excavated and aggregate base installed on Monday August 13th.. Notices have been passed out in anticipation of this work
  • Tuesday the water connection at Landwehr and Crestwood will be completed.
  • Roadway excavation and aggregate base course installation from Sussex Lane to 3924 Crestwood. 
  • Thursday set string line for the curbs and Friday start the curb pour for phase two
     

    The roadway reconstruction phase is still in full swing and working on the first of three phases for the concrete curb & gutter / asphalt paving operations. During this phase, resident with new concrete curb & gutter will be without driveways access until Tuesday, August 21st, if all goes as planned and weather allows for construction operations. We understand this is a huge inconvenience to each of the residents without driveways access; therefore, we are doing everything possible to minimize it to the greatest extent possible. Driveway access is for an extended period of time to allow for all the work to be completed at one time in lieu of staggered driveways restrictions several times over the next few weeks. Once access is restored, a majority of the roadway work in front of your home will be completed, including the first layers of asphalt binder which will significantly reduce the amount of dust and provide for a smooth driving surface. 

 
Once the work in Phase II is completed, the next phase of roadway reconstruction will begin. That section will be from 3921 Crestwood to Pfingsten Road.

Thank you to all those  residents without driveway access over the past week, your patience and understanding is greatly appreciated.