Completed water service replacements for entire
project
·
Connected new water main to existing water main
along side streets
·
Abandoned existing water main along Crestwood
Drive
·
Performed sanitary sewer service replacements as
needed.
·
General site clean-up
Work Anticipated to be performed next week, July 2nd
to July 6th
·
No work anticipated to be performed on-site all
week due to July 4th Holiday
·
General site clean-up, as needed.
The underground utility portion of the project is mostly
completed at this time. The contractor will have a few sanitary sewer services
to complete, minimal storm sewer installation, and one final water main
abandonment to complete.
Following the July 4th Holiday, the contractor
will be transitioning to the roadway reconstruction phase of the project.
This work will include removing the remaining concrete pavement, excavating the
existing base materials until a stable base is established, installing new base
materials, concrete curb & gutter on both sides of the street, and new
asphalt pavement. The roadway excavation will be broken up into sections
to minimize the inconvenience to residents to the greatest extent possible.
However, the roadway will be impassible in the areas they are working during
the day, with access to driveways and roadway restored at the end of each day.
The time it will take to perform this work will largely depend on the amount of
excavation needed to get to a stable base material. Additional information will
be provided to residents as the schedule is finalized and provide parking and
driveway restrictions.
Thanks again for all your understanding as the project moves
into the next phase of construction and the various inconveniences that you
will experience.
Have a safe and enjoyable July 4th Holiday.