Work Performed:
This week
- Finishing sod preparation along the length of the project
- Reinstalling signs throughout the project
Work Anticipated to be performed, October 8th to October 12th.
- Weather permitting the contractor will be working on sod. Sod installation is backed up due to wet weather.
- once sod and punch list are complete Bituminous Paving will be scheduled
Thank you in advance to all the residents on Crestwood for your patience throughout the project. Project completion is nearing and the disruption to your daily activities will soon end. Once again Thank You