Work Performed This Week, April 23rd to April
27th
·
Construction lay-out of improvements – These are
the wooden stakes with ribbon you see along the street. Please do not remove as
they are an important part of the construction process.
·
Saw-Cutting the existing concrete pavement in locations
of the proposed underground utility improvements.
Work Anticipated to be performed next week, April 30th
to May 4th.
·
Mobilization of equipment and material
deliveries.
·
Start underground utility construction.