Friday, August 24, 2018

Work Performed:


·              Finished excavation and undercuts in phase 2
  • curbs and driveways in phase 2 complete
 

Work Anticipated to be performed, August 27th to August 31st  



  • Monday, tentatively fine grade aggregate base.
  • Tuesday, tentatively pave Binder in Phase 2
  • Phase 3 construction will tentatively begin middle of next week. phase 3 includes the balance of the project moving east to Phingston Rd.

The roadway reconstruction phase is still in full swing and working on the second of three phases for the concrete curb & gutter / asphalt paving operations. Monday weather the contractor will be fine grading stone and then paving of phase 2. Phase 3 contructionWeather permitting Curb and driveways are tentatively planned for phase 3  the week of September 4, 2018.  We understand this is a huge inconvenience to each of the residents without driveways access; therefore, we are doing everything possible to minimize it to the greatest extent possible. Driveway access is for an extended period of time to allow for all the work to be completed at one time in lieu of staggered driveways restrictions several times over the next few weeks. Once access is restored, a majority of the roadway work in front of your home will be completed, including the first layers of asphalt binder which will significantly reduce the amount of dust and provide for a smooth driving surface. 



 
T Thank you in advance to all those  residents without driveway access for the next twelve days, your patience and understanding is greatly appreciated

Friday, August 17, 2018


Work Performed:


·        Excavation and under cuts in phase 2
  •  Tuesday the water connection at Landwehr and Crestwood will be completed.
  • Started installing the string line for curb instalation

 

Work Anticipated to be performed, August 20th to August 24th
 



 
  • Friday set string line for the curbs and Friday start the curb pour for phase two.
  • Monday weather permitting the contractor will start to pour new curbs in phase 2



The roadway reconstruction phase is still in full swing and working on the second of three phases for the concrete curb & gutter / asphalt paving operations. Monday weather permitting the contractor will start to pour new curbs in phase 2. This phase, resident in Phase 2 will be without driveway access until Thursday, August 30th, if all goes as planned and weather allows for construction operations. We understand this is a huge inconvenience to each of the residents without driveways access; therefore, we are doing everything possible to minimize it to the greatest extent possible. Driveway access is for an extended period of time to allow for all the work to be completed at one time in lieu of staggered driveways restrictions several times over the next few weeks. Once access is restored, a majority of the roadway work in front of your home will be completed, including the first layers of asphalt binder which will significantly reduce the amount of dust and provide for a smooth driving surface. 

 
Once the work in Phase II is completed, the next phase of roadway reconstruction will begin. That section will be from 3921 Crestwood to Pfingsten Road.

Thank you in advance to all those  residents without driveway access for the next twelve days, your patience and understanding is greatly appreciated.

Friday, August 3, 2018

Excavation and Curbs opngoing in Phase II


Work Performed:


·        Grading of new aggregate base in Phase I
  • Bituminous Binder course complete in phase one
 

 

Work Anticipated to be performed, August 13th to August 17th

·        The intersection of Sussex and Crestwood will be excavated and aggregate base installed on Monday August 13th.. Notices have been passed out in anticipation of this work
  • Tuesday the water connection at Landwehr and Crestwood will be completed.
  • Roadway excavation and aggregate base course installation from Sussex Lane to 3924 Crestwood. 
  • Thursday set string line for the curbs and Friday start the curb pour for phase two
     

    The roadway reconstruction phase is still in full swing and working on the first of three phases for the concrete curb & gutter / asphalt paving operations. During this phase, resident with new concrete curb & gutter will be without driveways access until Tuesday, August 21st, if all goes as planned and weather allows for construction operations. We understand this is a huge inconvenience to each of the residents without driveways access; therefore, we are doing everything possible to minimize it to the greatest extent possible. Driveway access is for an extended period of time to allow for all the work to be completed at one time in lieu of staggered driveways restrictions several times over the next few weeks. Once access is restored, a majority of the roadway work in front of your home will be completed, including the first layers of asphalt binder which will significantly reduce the amount of dust and provide for a smooth driving surface. 

 
Once the work in Phase II is completed, the next phase of roadway reconstruction will begin. That section will be from 3921 Crestwood to Pfingsten Road.

Thank you to all those  residents without driveway access over the past week, your patience and understanding is greatly appreciated.