Sunday, July 15, 2018

Roadway Reconstruction to Begin

Work Performed:
·         Minimal work completed due to scheduling conflicts and waiting on needed permits to work along Landwehr Road.
·         Resumed performing sanitary sewer service replacements as planned
·         Resumed storm sewer installation within cul-de-sacs
·         Started making storm sewer repairs as previously determined.

Work Anticipated to be performed, July 16th to July 20th  
·         Complete storm sewer replacement
·         Begin roadway excavation.

The contractor will be transitioning to the roadway reconstruction phase of the project.  This work will include removing the remaining concrete pavement, excavating the existing base materials until a stable base is established, installing new base materials, concrete curb & gutter on both sides of the street, and new asphalt pavement.  The roadway excavation will be broken up into sections to minimize the inconvenience to residents to the greatest extent possible. However, the roadway will be impassible in the areas they are working during the day, with access to driveways and roadway restored at the end of each day. The time it will take to perform this work will largely depend on the amount of excavation needed to get to a stable base material. Additional information will be provided to residents during the roadway reconstruction phase.

Thank you for your understanding and patience during some of the unexpected delays.

Friday, June 29, 2018

Underground Work Mostly Completed. No Work On-site week of July 2nd due to Holiday

Work Performed Last Week, June 25th to June 29th
·         Completed water service replacements for entire project
·         Connected new water main to existing water main along side streets
·         Abandoned existing water main along Crestwood Drive
·         Performed sanitary sewer service replacements as needed.
·         General site clean-up

Work Anticipated to be performed next week, July 2nd to July 6th
·         No work anticipated to be performed on-site all week due to July 4th Holiday
·         General site clean-up, as needed.

The underground utility portion of the project is mostly completed at this time. The contractor will have a few sanitary sewer services to complete, minimal storm sewer installation, and one final water main abandonment to complete.

Following the July 4th Holiday, the contractor will be transitioning to the roadway reconstruction phase of the project.  This work will include removing the remaining concrete pavement, excavating the existing base materials until a stable base is established, installing new base materials, concrete curb & gutter on both sides of the street, and new asphalt pavement.  The roadway excavation will be broken up into sections to minimize the inconvenience to residents to the greatest extent possible. However, the roadway will be impassible in the areas they are working during the day, with access to driveways and roadway restored at the end of each day. The time it will take to perform this work will largely depend on the amount of excavation needed to get to a stable base material. Additional information will be provided to residents as the schedule is finalized and provide parking and driveway restrictions.

Thanks again for all your understanding as the project moves into the next phase of construction and the various inconveniences that you will experience.

 

Have a safe and enjoyable July 4th Holiday.

Monday, June 18, 2018

Water Service Replacements On-Going.

Work Performed Last Week, June 11th to June 15th  
·         Water service replacements along Crestwood.

Work Anticipated to be performed next week, June 18th to June 22nd  
·         Continue with water service replacements along Crestwood Drive
·         Water service replacements within the cul-de-sacs
·         Connection between new water main and existing water main at Carousel Drive (East) and Crestwood Drive.
·         Storm sewer improvement with cul-de-sacs as water service replacements are performed.

The contractor will continue water service replacements this week. The contractor is anticipating to complete the water services along Crestwood Drive and begin working in the cul-de-sacs. Water services will be replaced from the new water main to the existing valve and box located in front of each home. During the water service replacement, water to individual homes will be shut-off for approximately 1-2 hours while the transition from the old service to the new service is made. The contractor will notify each resident individually regarding the approximate time and day of the water shut-off prior to turning off the water.

The water service replacements within the cul-de-sacs will be time consuming due to the routing and length of each service.  It will be increasingly difficult to travel through the cul-de-sacs as this work is on-going.  Please be patient while driving through these areas.

Thanks again for all your assistance while you live through construction in your area.

Friday, June 8, 2018

Water Service Replacements to Continue

Work Performed Last Week, June 4th to June 8th
·         Received necessary approvals to place the new water main into service.
·         Made connections to existing water main near Russet Way and Sussex Lane
·         Started water service replacements
·         Completed storm sewer along Crestwood Lane
·         Completed sanitary sewer main line repair

Work Anticipated to be performed next week, June 11th to June 15th
·         Continue with water service replacements, anticipated to take 1-2 weeks to complete.
·         Storm sewer improvement with cul-de-sacs as water service replacements are performed.

The contractor will continue water service replacements this week. Water services will be replaced from the new water main to the existing valve and box located in front of each home. During the water service replacement, water to individual homes will be shut-off for approximately 1-2 hours while the transition from the old service to the new service is made. The contractor will notify each resident individually regarding the approximate time and day of the water shut-off prior to turning off the water.

We appreciate your patience during construction and the disruptions in water service.

Tuesday, June 5, 2018

Water Service Replacements to Begin

Work Performed Last Week, May 29th to June 1st
·         Completed testing of water main along entire project site
·         Continued with storm sewer installation.
·         No work performed on-site on Thursday and Friday due to scheduling conflicts.

Work Anticipated to be performed next week, June 4th to June 7th
·         Continue with storm sewer installation
·         Perform sanitary sewer main repairs as needed.
·         Begin water service replacements

The contractor will begin water service replacements this week. Water services will be replaced from the new water main to the existing valve and box located in front of each home. During the water service replacement, water to individual homes will be shut-off for approximately 2-3 hours while the transition from the old service to the new service is made. The contractor will notify each resident individually regarding the approximate time and day of the water shut-off prior to turning off the water.

Thanks again for all your patience and understanding as you deal with the dust, travel delays, and other inconveniences of living within a construction area.

Tuesday, May 29, 2018

Water Main Installation Completed. Testing of Water Main On-Going

Work Performed Previously
·         Installed new 8-inch water main from Pfingsten Road to Landwehr Road, including cul-de-sacs
·         Started necessary testing of new water main from Pfingsten Road to Sussex Lane
·         Started storm sewer installation

Work Anticipated to be performed next week, May 29th to June 1st
·         Continue with water main testing from Pfingsten Road to Sussex Lane
·         Begin water main testing from Sussex Lane to Landwehr Road
·         Continue with storm sewer installation.

As you are aware, the weather over the past few weeks has not been favorable with the frequent rain events. Construction has been delayed, but everything is being done to keep the project on schedule to the greatest extent possible.

Thanks again for all your patience and understanding.

Friday, May 11, 2018

Construction Started. Water Main Installation On-Going

Work Performed This Week, May 7th to May 11th
·         Saw-cutting of existing concrete pavement in locations of water main installation.
·         Closed-Circuit televising of existing storm and sanitary sewers
·         Began water main installed near Landwehr Road and working east toward Pfingsten Road

Work Anticipated to be performed next week, May 14th to May 18th
·         Continue with water main installation.

As construction has started, there is an increase of construction traffic along the roadway. Please use caution as you driving along the site and backing out of your driveway.  It is anticipated that some settlement will occur over the gravel trenches that were previously excavated.  Please be assured everything will be done to keep those areas as smooth as possible, but please drive slowly.  We are also committed to reducing the amount of dust to the greatest extent possible by utilizing water and street sweeping.

Thanks again for all your patience during the construction operations.