Received necessary approvals to place the new
water main into service.
·
Made connections to existing water main near
Russet Way and Sussex Lane
·
Started water service replacements
·
Completed storm sewer along Crestwood Lane
·
Completed sanitary sewer main line repair
Work Anticipated to be performed next week, June 11th
to June 15th
·
Continue with water service replacements, anticipated
to take 1-2 weeks to complete.
·
Storm
sewer improvement with cul-de-sacs as water service replacements are performed.
The contractor will continue water service replacements this
week. Water services will be replaced from the new water main to the existing
valve and box located in front of each home. During the water service
replacement, water to individual homes will be shut-off for approximately 1-2
hours while the transition from the old service to the new service is made. The
contractor will notify each resident individually regarding the approximate
time and day of the water shut-off prior to turning off the water.
We appreciate your patience during construction and the disruptions in water service.