Construction Started. Water Main Installation On-Going

Work Performed This Week, May 7th to May 11th
·         Saw-cutting of existing concrete pavement in locations of water main installation.
·         Closed-Circuit televising of existing storm and sanitary sewers
·         Began water main installed near Landwehr Road and working east toward Pfingsten Road

Work Anticipated to be performed next week, May 14th to May 18th
·         Continue with water main installation.

As construction has started, there is an increase of construction traffic along the roadway. Please use caution as you driving along the site and backing out of your driveway.  It is anticipated that some settlement will occur over the gravel trenches that were previously excavated.  Please be assured everything will be done to keep those areas as smooth as possible, but please drive slowly.  We are also committed to reducing the amount of dust to the greatest extent possible by utilizing water and street sweeping.

Thanks again for all your patience during the construction operations.