Saw-cutting of existing concrete pavement in
locations of water main installation.
·
Closed-Circuit televising of existing storm and
sanitary sewers
·
Began water main installed near Landwehr Road
and working east toward Pfingsten Road
Work Anticipated to be performed next week, May 14th
to May 18th
·
Continue with water main installation.
As construction has started, there is an increase of
construction traffic along the roadway. Please use caution as you driving along
the site and backing out of your driveway. It is anticipated that some
settlement will occur over the gravel trenches that were previously
excavated. Please be assured everything will be done to keep those areas
as smooth as possible, but please drive slowly. We are also committed to
reducing the amount of dust to the greatest extent possible by utilizing water
and street sweeping.
Thanks again for all your patience during the construction
operations.