Friday, August 24, 2018

Work Performed:


·              Finished excavation and undercuts in phase 2
  • curbs and driveways in phase 2 complete
 

Work Anticipated to be performed, August 27th to August 31st  



  • Monday, tentatively fine grade aggregate base.
  • Tuesday, tentatively pave Binder in Phase 2
  • Phase 3 construction will tentatively begin middle of next week. phase 3 includes the balance of the project moving east to Phingston Rd.

The roadway reconstruction phase is still in full swing and working on the second of three phases for the concrete curb & gutter / asphalt paving operations. Monday weather the contractor will be fine grading stone and then paving of phase 2. Phase 3 contructionWeather permitting Curb and driveways are tentatively planned for phase 3  the week of September 4, 2018.  We understand this is a huge inconvenience to each of the residents without driveways access; therefore, we are doing everything possible to minimize it to the greatest extent possible. Driveway access is for an extended period of time to allow for all the work to be completed at one time in lieu of staggered driveways restrictions several times over the next few weeks. Once access is restored, a majority of the roadway work in front of your home will be completed, including the first layers of asphalt binder which will significantly reduce the amount of dust and provide for a smooth driving surface. 



 
T Thank you in advance to all those  residents without driveway access for the next twelve days, your patience and understanding is greatly appreciated